Decision
Analysis
outcome: The Committee agreed to refurbish Bourne Hall Lodge for residential accommodation and to fund the refurbishment budget of up to £340,000 from S106 developer funds.
summary: The decision involves refurbishing Bourne Hall Lodge for residential accommodation.
topline: The Strategy and Resources Committee has decided to refurbish Bourne Hall Lodge for residential accommodation.
reason_contentious: This issue may be contentious as it involves the use of developer funds for refurbishment and potential impact on the local community.
affected_stakeholders: ["residents", "developers", "local community"]
contentiousness_score: 6
political_party_relevance: There are no mentions or implications of political parties in the decision.
URL: https://democracy.epsom-ewell.gov.uk/ieDecisionDetails.aspx?ID=1453
Decision Maker: Strategy and Resources Committee
Outcome:
Is Key Decision?: No
Is Callable In?: No
Purpose:
Content: Following consideration, the Committee unanimously resolved to: (1) Agree for Bourne Hall Lodge to be refurbished for residential accommodation, as detailed in Option 1 (Appendix 2, paragraphs 1.1 – 1.12 of the report). (2) Agree to fund the refurbishment budget of up to £340,000 from S106 developer funds. (3) Nominate and authorise the Head of Property & Regeneration, Head of Housing & Community in consultation with the Director of Corporate Services and Head of Legal, to take all necessary actions further to the above decision being made that commit resources, as is necessary and appropriate, to progress the selected option to completion.
Date of Decision: July 15, 2025