Decision
URL: https://milton-keynes.moderngov.co.uk/ieDecisionDetails.aspx?ID=1784
Decision Maker: Cabinet
Outcome:
Is Key Decision?: No
Is Callable In?: No
Purpose: To consider approving the funding arrangements and procurement of the main works to extend the H10 grid road.
Content: RESOLVED: 1.1. That funding of £14.5m (including £1.6m approved to date) for the delivery of the H10 extension, as shown on the annexed plans, be provided from the Tariff Programme. 1.2. That additional resource allocation and spend approval of £12.9m is approved in the capital programme. 1.3. That a contractor for the main works be procured through further competition utilising the Midlands Highway Alliance (MHA) MSF4 Construction Medium Schemes Framework. 1.4. That authority be delegated to the Director of Planning and Placemaking, in consultation with the Director of Finance and Resources, to finalise the arrangements for: a) entering into a contract for the delivery of the main H10 extension works; and b) the completion of legal agreements as required with Milton Keynes Development Partnership (MKDP), Milton Keynes Community Foundation (MKCF) and Connolly, to allow for the works to be delivered.
Date of Decision: November 4, 2025