Decision
URL: https://democracy.blackburn.gov.uk/ieDecisionDetails.aspx?ID=1236
Decision Maker:
Outcome: Recommendations Approved
Is Key Decision?: No
Is Callable In?: No
Purpose:
Content: RESOLVED (1) That the progress made in the delivery of the King George’s Hall construction programme with the aim of fully re-opening KGH in Autumn 2026 be noted. (2) That the request for £4.5 million additional funding for this initiative by utilising and re-allocating the Council’s secured Local Growth Funds and Pride in Place Impact Funding to deliver the strategic works and outcomes, as set out in this report, be approved.
Date of Decision: December 11, 2025