Decision
URL: https://democracy.epsom-ewell.gov.uk/ieDecisionDetails.aspx?ID=1547
Decision Maker: Strategy and Resources Committee
Outcome:
Is Key Decision?: No
Is Callable In?: No
Purpose:
Content: Following consideration, the Committee resolved with four votes for and three votes against to: (1) Note the update and progress made as set out in the report. (2) Agree to complete the more detailed Phase 2 work at a cost of £30,000 as set out in paragraphs 4.1 to 4.4 of the report. (3) Agree to release the £30,000 Phase 2 funds from the LGR Reserve.
Date of Decision: March 17, 2026