Decision

URL: https://democracy.towerhamlets.gov.uk/ieDecisionDetails.aspx?ID=7957

Decision Maker: Cabinet

Outcome: Recommendations Approved

Is Key Decision?: Yes

Is Callable In?: No

Purpose: This report is seeking approval for £11.3m of additional funding to complete works on the Maltings & Brewster estate and to directly award the third phase of work to Wates Property Services. This will increase the cost of these works to £22.8m. These essential building safety works have comprised the removal and replacement of the external wall insulation (EWI) and structural works on the blocks which commenced in 2017.  

Content:

Date of Decision: March 27, 2026