Decision

URL: https://rutlandcounty.moderngov.co.uk/ieDecisionDetails.aspx?ID=1015

Decision Maker: Strategic Director for Places

Outcome: Recommendations Approved

Is Key Decision?: No

Is Callable In?: No

Purpose: To enable the release of the £193,097.06 contribution secured from Bloor Homes towards the provision of a roundabout on Leicester Road, Uppingham, appropriate trigger points have been agreed and are incorporated into the final version of the Section 278 agreement for the development by Davidsons Developments which is to be signed and sealed. The agreed triggers are as follows: 50% payable within 20 working days of commencement of the highway works (subject to notification in writing of such from the developer) The remaining 50% payable within 20 working days of issue of the Final Certificate. This approach ensures the funding is aligned with the delivery of the required highway infrastructure and supports the mitigation of cumulative development impacts.

Content:

Date of Decision: June 26, 2026