Purpose: Following a competitive procurement exercise, via a mini competition on the Procure Partnerships Framework, Stepnell were identified as the preferred contractor. A decision was taken in September 2023 by the Service Director for Economic Growth, in consultation with the Cabinet Member for Economic Growth, and Cabinet Member for Town Centres and Visitor Economy, to award a contract to Stepnell Ltd. on a two-stage design and build basis with Pre-Construction Services Agreement. That decision covered the first stage of the contract, with a recommendation that a further officer decision be taken to enter the second stage of the contract (this approval).
Content:
Date of Decision: December 9, 2024